IV. Structural constraints: Limits of the transmission
system.
There seem to have been few questions raised regarding the
capability of the existing transmission system to support
this project. Without a detailed transmission integration
study by the ISO New England, it is difficult to say with
any certainty what the transmission constraints on such
extensive new power generation in southern Vermont may be.
Nonetheless, a few conclusions can be drawn from examining
the capacity of the transmission system in the region and
the location of current generating units.
NEPOOL has identified the 345 kV transmission tie from
Vermont Yankee south to Northfield as a potentially limiting
interface. This means that this line does not have much
extra capacity to deliver energy south into Massachusetts
beyond its current commitment. In addition to power from
Vermont Yankee flowing south, New England draws power from
Hydro Quebec and New York from northwestern Vermont. This
need to import electricity, through Vermont, to meet growing
demand in the rest of New England constrains the system
considerably. We do know, as discussed above, that most of
the energy from these plants would have to be exported from
Vermont since the local market cannot absorb 1,350 MW of
additional power. The primary interface from southern
Vermont to the rest of NEPOOL is through the Vermont Yankee
line to Northfield. Since this link is already a potential
bottleneck, it is inconceivable that this interface can
absorb all that additional output. The interconnection with
New York from the Rutland region is quite weak and could
carry only a small fraction of the output of the Rutland
plant.
Another constraint is the transmission tie between Vermont
Yankee and the Rutland area. While this particular tie may
be sufficient to carry a portion of Vermont Yankee's 500 MW
of output to the Rutland area, it is probably not capable of
carrying the bulk of the power from the proposed Rutland
plant south to Massachusetts.
The capability of the transmission system in this context is
not easily determined. It requires an analysis that lies far
beyond the scope of this paper. Nonetheless, these
observations about capacities of the existing transmission
lines in the area should be regarded as a major potential
obstacle in the path of the proposed project. The sheer size
of the proposed power plants, and the lack of available
markets in the Rutland and Bennington areas, are likely to
require the construction of new transmission lines to carry
the energy to the rest of New England. To minimize impact
from such a project, it would be beneficial to site the
transmission alongside the gas pipeline. However, this may
not be a viable solution because the southwestern portion of
Vermont does not have the strong interconnection with the
rest of New England that would be needed. A connection with
the New York - Massachusetts 230 kV line is possible, but
again, it is altogether unclear whether this connection,
combined with existing ties out of Rutland would be
sufficient.
New generation would potentially displace some of the power
currently being imported from New York and Hydro-Quebec. In
that sense it is possibly better to bring the generation
closer to the where the greatest demand is, which is
Massachusetts. However, this does not resolve the underlying
transmission constraint in the inter-tie with Massachusetts.
Another problem is that if the proposed plants were built,
they would have to curtail the availability of power from
Hydro-Quebec because transmission capability is limited.
This may seem fine in context of current prices for Quebec
power. Nonetheless, considering the low cost-base of this
power, the likely re-negotiation of contracts or other new
arrangements at some point in the future, and the fact that
high-voltage lines to Quebec are already in place, it may
not be in the long-term interest of Vermont to restrict
access to this source. Building the Rutland plant would be a
further hindrance to increasing such imports unless
transmission capacity south of Rutland were expanded
dramatically.
|