May 27, 1999
Mr. Bruce Roloson
Manager Sales and Marketing
Southern Vermont Natural Gas
P.O. Box 160
Rutland, Vermont 05702-0160
Dear Mr. Roloson:
I am writing to express my concerns about the
apparent delay in your timetable for ANR's review
of SVNG's natural gas distribution project. As you
are aware, the Agency of Natural Resources has
expended considerable time and resources to
prepare for the necessary field review that will
be required if and when you seek regulatory
approval for your gas pipeline project. These
resources were expended in good faith reliance on
the timetable that you presented, whereby
fieldwork was to commence and conclude during the
1999 construction season. Inherent to our
discussions and to any chance for accommodating a
one season review, is the necessity that such
review be commenced early in the season. While I
never promised that ANR could complete its review
within your proposed timeframe, I nonetheless
directed staff to make all necessary preparations
and arrangements to accommodate your timetable.
In reliance on our discussions, ANR has sought and
received approval to hire and train as many as six
temporary staff positions. These positions were
advertised and a roster of potential candidates
was completed more than a month ago. As
prospective candidates steadily notify us that
they are pursuing other opportunities, our roster
is becoming somewhat irrelevant. State personnel
requirements provide that a job posting must be
filled within a reasonable amount of time
afterwhich the positions are lost and the process
must commence anew. The current temporary
positions expire June 3. Although there is a
mechanism to extend the positions for up to one
month, approval of such an extension is not
automatic and may take some arm twisting with the
personnel department. Before I am willing to
engage in such an exercise, I need greater
assurances that our considerable efforts to date
were not in vain.
ANR remains willing and able to staff up to
provide an expeditious review of your project. The
longer the delay, the less likely it becomes that
field review can be completed in one season.
Please contact me should you care to further
discuss this matter.
Sincerely,
Scott Johnstone
Deputy Secretary