From the File of Andy Raubvogel
General Counsel for Agency of Natural Resources
Handwritten Notes taken 9/30/98
Phase I
1080 mw Rutland
270 mw Bennington
Phase II
Pipeline Rutland to Killington
Phase III
Pipeline Rutland to Middlebury
Phase IV
Pownal to Mass. to Brattleboro
Phase V
Brandon to Ticonderoga
Phase VI
Rutland to Barre/Montpelier
All Phases ^ 10 years
NYSEG says they can build gate stations for $300-400,000
less than Iroquois
NYSEG will bid to build Iroquois portion
AOT wants them in RR ROW or under the track.
NYSEG tries for 50% conversion rate by five years
Have seen up to 80% conversion rate within 10 years.
MOU for payback prior to initiation of 248 proceeding.
Initial scoping of route ^ could be done this Fall by existing
ANR personnel ^ wouldn,t need MOU right away.
|